The Reimagined Colony Square | #csreimagined

Our Story

Originally built in the 1970's, Colony Square has stood the test of time remaining in the heart of Midtown for nearly 50 years. The property underwent a reimagination starting in 2018 and fully reopened in 2021. An urban, amenity-rich and arts-infused place to gather and soak up Midtown’s vibe. 

What originally started out as just two office towers, has now turn into nearly one million square feet of class A office space, 160,000 square feet of best-in-class retail, restaurants and entertainment, a 20,000-square-foot food hall featuring an all local lineup of culinary talent, 40,000 square feet of open-air greenspace, 262 luxury residences and a 466-room hotel

Timeline
October 2017
Groundbreaking
November 2017
Demolition and foundation work
December 2017
Demolition, foundation work, closing of The Atrium
January 2018
Houlihan's Demolition and foundation work
February 2018
Houlihan's Demolition, Reimagination of Building 100 + The Grove
March 2018
Reimagination of Building 100 + The Grove
April 2018
Interior mall demolition + reimagination of Building 100
May 2018
Reimagination of Building 100
June 2018
Reimagination of Building 100
July 2018
Reimagination of Building 100
August 2018
Reimagination of Building 100
September 2018
Interior demo of Atrium and Main Level of Building 400, Reimagination of Building 100 continues
October 2018
Building 100 Entrance + Lobby completion
November 2018
Building 400 Lobby Demolition + Reimagination
December 2018
Building 400 Lobby & Plaza Level Demolition + Reimagination
January 2019
Demolition + Reimagination of Building 400 Entrance + Lobby
February 2019
Reimagination of Building 400, and Demolition of Atrium + Removal of Glass, Construction of The Grove
March 2019
Reimagination of Building 400, Demolition of Atrium + Mall, Construction of The Grove
April 2019
Former Atrium + Mall demolition, Crane in place for vertical construction of Food Hall + IPIC
May 2019
Vertical construction of Food Hall + IPIC, opening of The Grove, and opening of Bldg 400 entrance + lobby
June 2019
Construction of Food Hall & IPIC, continued demo of Bldg 400, steel erection for Bldg 300
July 2019
Vertical construction of Bldg 300, ongoing build-out of Food Hall & IPIC
August 2019
Ongoing build-out of Food Hall + IPIC, Topping out Bldg 300, opening of Loop Lounge
September 2019
Building 300 concrete pouring, steel framing, ongoing buildout of iPic + Food Hall
October 2019
Ongoing buildout of Building 300, Spaces, iPic + Food Hall
November 2019
Bldg 300 glass install, Bldg 400; 2nd floor band completion, iPic exterior paneling install, ongoing build-out iPic + Food Hall
December 2019
Ongoing build-out of iPic (including exterior paneling install) + Food Hall, Bldg 300, demo of former Plaza
January 2020
Sidewalk demo, Bldg 400 base construction, Ongoing build-out of iPic (including exterior paneling install) + Main & Main, Bldg 500 site prep
February 2020
Steel erected for Bldg 500, Exterior prep for Bldg 300, Ongoing construction for Bldg 400 base, iPic, and Food Hall
March 2020
Bldg 500 goes vertical; steel framing, Bldg 300 exterior paneling, ongoing construction of iPic, Rumi's and Bldg 400 restaurants
April 2020
Topping off of Building 500, Buildout of Concierge + The Plaza, ongoing construction of iPic, Rumi's and Bldg 400 restaurants
May 2020
Completion of Building 300 and Concierge, ongoing construction of iPic, Rumi's, Bldg 400 retail spaces and Building 500
June 2020
Completion of Building 300 + Concierge, ongoing construction of iPic, Rumi's, Bldg 400 retail spaces and Bldg 500
July 2020
Opening of Concierge, ongoing construction of iPic, Rumi's, Bldg 400 retail spaces and Bldg 500
August 2020
Completion of LED Screen + Von Dom Sculpture Garden, ongoing build out of iPic, Rumi's, Bldg 400 retail spaces and Bldg 500
September 2020
Building 500 construction and buildout of IPIC continues, Plaza completion
October 2020
Completion of The Plaza + Brown Bag Seafood. West Retail, Bldg 500 + interior build of Politan Row at Colony Square build-out continues
November 2020
Ongoing build out of iPic, American Barber, Bldg 500 and interior build of Politan Row at Colony Square (food hall)
December 2020
IPIC Opens, Bldg 500 and interior build of Politan Row at Colony Square (food hall) continues
January 2021
West Retail Storefront completion, Interior build out of Bldg 500 and Politan Row at Colony Square (food hall) continues
February 2021
Politan Row at Colony Square (food hall) interior construction continues, Jones Day build out continues
March 2021
Jones Day signage install + buildout, hardscapes and landscaping around Bldg 500, Politan Row at Colony Square (food hall) build continues
April 2021
Completion of Jones Day, Politan Row at Colony Square (food hall) build out continues
May 2021
Opening of Jones Day, Saints & Council, H&F, Sweetgreen, and Lush continue build out
June 2021
Completion of Politan Row at Colony Square (Opened June 24, 2021)
July 2021
Completion + Grand Opening of Serena Pastificio (Opened July 13, 2021)
August 2021
Ongoing buildout of Sweetgreen + King Of Pops, construction of Saints + Council, Lush Nail Bar, Rumi's + H&F
#CSReimagined Flythru